Information Services@ANU

Division of Information Initiated Projects

2008 - 2009

In addition to maintaining all the current information services available to the ANU community, the Division of Information is engaged in numerous projects at any given time. A project is an endeavour of limited duration in which a unique product or service is created. From this page you can access descriptions of all current DOI projects.

Archives

Archives Management Database - Stage 2 (data migration)

  • Priority – High
  • Progress Status – In progress (stage 1 completed and testing software underway) and not yet funded (for Enterprise Systems staff)
  • Target Commencement – March to June 2009 (for Enterprise Systems bit)

Survey Of Audiovisual Holdings

  • Priority – High
  • Progress Status – In progress (for the bits we’re doing in-house) and not yet funded (for the external consultant
  • Target Commencement – September to October 2009 (for external consultant)

Archives Management Database – Stage 3 (capture of hard copy data etc) dependent on Stage 2 completion. Not yet funded

  • Priority – High
  • Progress Status – Dependent on Stage 2 completion
  • Target Commencement – 2010. Dependent on Stage 2 completion

Audiovisual Holdings: Recommended Action From Survey Report

  • Priority – Unknown but any recommended data migration likely to be High. Not yet funded
  • Progress Status – Unknown
  • Target Commencement – 2010 Note: Archives Management Database - Stage 2 and Survey Of Audiovisual Holdings must be completed before Archives Management Database – Stage 3 and Audiovisual Holdings can commence.

Digital Resource Services

Digital Lecture Delivery

  • High Priority; Approved
  • Robust replacement for current system. Develop lecture capture and
    retrieval mechanisms in limited number of theatres by end of year,
    expanding across campus in 2009.

Academic Self-Submission

  • High Priority; Approved & funded (from within DRS budget), in progress.
  • Develop simple submission system for academic materials which can then
    be attached to a repository application and an external (to the project)
    metadata store.

RP3 (AKA SP7)

  • Medium Priority; Approved & funded (from within DRS budget), in progress.
  • Unifying view & controller (a la MVC) of academic profiles, publications
    and project data from holdings across campus. To mesh with ePortfolios,
    among others.

Virtual Video Recording (VVR)

  • Medium Priority; Approved & funded (from within DRS ex-APSR funds), in
    progress.
  • Television/satellite content capture and replay system. Related work
    being undertaken by Netcomms.

Open Journal System

  • Medium Priority; Approved & funded (from within DRS ex-APSR funds), near
    completion.
  • Trial the OJS eJournal application with selected early adopters on
    campus. It is suitable for current purposes and responsibility/ownership
    need to be reallocated.

Academic promotions

  • High Priority; in progress.
  • Secure storage and retrieval of documentation supporting academics'
    promotion bids. This is a repeating activity and should probably be
    turned into a process.

ePress

Further develop the conversion process within the technical model to allow more sophisticated and complex presentation of content from XML source file

  • Priority – Medium
  • Project Status – Planning, have commenced some scripting
  • Target Commencement – Beginning of January 2009 completion – Mid February 2009

Refine use of existing download statistics-gathering program (Webalizer) in order to filter and exclude impact of internet robots, automated processes, crawlers and spam-bots.

  • Priority – High
  • Project Status – Planning
  • Target Commencement – Beginning of January 2009, completion – asap, this will depend on Allan’s priorities

Library User Services

  • Project Priority (H=High, M=Medium, L=Low)      
  • Project status  (P=Planning, A=Approved, AF=Approved & Funded, IP=In Progress, C=Complete)
  • Target commencement & completion timeframe.

Project Name

Priority

Status

Start

Finish

Walk-in user access to catalogue & electronic resources

H

A

Q42008

Q42008

WebBridge (ILMS)

H

IP

Q22008

Q42008

ArticleReach (ILMS)

H

IP

Q22008

Q42008

AirPac (ILMS)

M

P

N/a

N/a

Library client user satisfaction survey (Rodski/Insync)

H

IP

Q32008

Q42009

Networks and Communications

  • Project Priority (H=High, M=Medium, L=Low)      
  • Project status  (P=Planning, A=Approved, AF=Approved & Funded, IP=In Progress, C=Complete)
  • Target commencement & completion timeframe.

Project Name

priority

status

start

finish

Wireless Network Next Generation

H

AF

Q208

Q409

Crisp Business Continuity/DR Site

H

AF

Q308

Q308

Accommodation Halls Structured Cabling to Cat6

H

AF

Q408

Q210

Network Management Systems Upgrade

H

AF

Q207

Q408

UPS Roll-out

H

AF

Q106

Q109

Communication Rooms Audit

H

AF

Q106

Q109

Next Generation Switch Upgrade

H

AF

Q106

Q209

eduroam

M

AF

Q207

Q308

Baseband Media Replacement

completed

Switch Visibility Implementation

completed

Video Conferencing Deployment

H

AF

Q107

Q408

Intrusion Detection & Prevention Hardware

H

AF

Q407

Q109

Wireless Network Analysis

completed

Core Services Upgrade

H

AF

Q308

Q408

Access & Security Policy to the edge

H

AF

Q108

Q209

Redundant Fibre Roll-out

H

AF

Q206

Q408

Unified Messaging

M

P

Q109

Q309

EC500

M

AF

Q308

Q308

IP Telephony Directory Function implementation

completed

Kioloa Communication Services Upgrade

H

AF

Q208

Q408

Resnet

completed

Gig. E & Hi-Fidelity IP Telephony Handsets

M

AF

Q308

Q408

VoWLAN Handsets

L

P

Q309

Q409

IPv6 (Advanced Comms.)

completed

Presence (Advanced Comms.)

M

AF

Q207

Q308

Web Streaming & ANU TV (Advanced Comms.)

H

AF

Q108

Q408

SIP (Advanced Comms.)

H

AF

Q208

Q408

Unified Communications Solutions

M

P

Q109

Q409

Emergency Communications System

H

AF

Q207

Q308

DR Radio/Optics Acton

M

AF

Q308

Q408

ANU Exchange Area Network

M

AF

Q106

Q416

LITSS Training Program

M

AF

Q208

Q308

Test Lab Build

Completed

Wireless Subnet Extension

H

AF

Q308

Q109

Networks and Server Layer Security Audit

M

AF

Q207

Q308

Wireless Traffic Control

H

AF

Q207

Q308

Core Bandwidth Upgrade

Completed

VPN re-Design

M

AF

Q408

Q408

Virtual Firewall Management

completed

Outreach          

Information Services Web Site – Redesign and Restructure

  • Priority – High
  • Project Status – In Progress. Designs have been completed. Structure and guidelines are currently being drafted.
  • Target Completion Date – Top level pages to be online by end of this year.

iGuide – Review and Redesign

  • Priority – High
  • Project Status: In Progress. Data is currently being collected as to how the iGuide is used and next year’s release will be adjusted based on this data.
  • Target Completion Date – Printed issues to be completed by 30 November. Web sites to be updated by beginning of Semester 1 2009.

Outreach Publications Knowledge Database

  • Priority – High
  • Project Status: Planning. Currently discussing options for creating one database that will contain content that can be used for a variety of publications and web sites.
  • Target Completion Date: Completion date has yet to be determined.

RP3 (aka: SP7)

  • Priority – Medium
  • Project Status: In-Progress. First draft of designs have been completed.
  • Target Completion Date: Completion date has yet to be determined.

Records

A pilot scheme to digitise and store hardcopy records is in the early planning stages. This is a major initiative which will provide for a staged approach towards Electronic Records Management.     

  • Medium Priority (benefits to be gained, but the University could continue working as is)
  • Project Status is In Progress (not sure of the funding that has been committed to the project other than the initial payments to Lateral Minds.
  • Target commencement date is 25 August and completion 21 November

Scholarly Information Resource Management

  • Project priority (H = High; M = Medium; L = Low)
  • Project status (P = Planning; A = Approved; AF = Approved and funded; IP = In progress; C = Complete)
  • Target commencement and completion timeframe

Project Name

Priority

Status

Start

Finish

Electronic Resource Management Module

M

IP

Q42006

Q42009

ILMS/ESP Interface Project (Stage 1)

H

IP

Q12007

Q32008

Collection Relocation Project (Stage 1)

H

IP

Q42006

Q12009

Backspace the collection in Chifley, Law, Menzies, Art and Music

H

IP

Q12008

Q42008

Installation of additional learning space (Chifley, Law, Menzies, Art)

H

IP

Q12008

Q12009

Last Copy Collection Retention Strategy

H

A

Q42007

Q42009

Repository of Learning Objects

M

IP

Q12006

Q12009

Digital Resource Discovery Project 2

M

IP

Q42006

Q42008

Replace Compactus in Rare Book Room

H

C

Q22008

Q22008

Re-accommodate material held in the Earth Sciences Library

L

P

Q42008

Q42008

Re-establish the Astronomy Library

H

IP

Q22008

Q42008

PRDLA

M

C

Q22008

Timor (on hold due to political situation)

M

On hold

Triennial valuation of the Rare Book Collection

H

P

Q42007

Q42010

Collection space management strategy

H

P

Q12009

Q2013

Expand staff work area at ANU print Repository

H

P

Q22009

Q22009

Re-accommodate material held in the Chemistry Library

M

P

2010

2010

Space Services

All projects are not DOI funded – Central

Projects

  • Breakdown and Corrective Maintenance (Ongoing).
  • Theatre lighting review and upgrade
  • Programmed building fabric maintenance – Carpet, painting etc.
  • Teaching and Learning Commons refurbishment program
  • Menzies Library foyer refurbishment Ongoing consultation with the University on interim staff accommodation arrangements, pending implementation of a long term plan.

Note:
The above are planned and funded through the Division’s maintenance levy set by the Universoty on an annual basis – 0.36% of CRV of buildings occupied by DOI. CRV of buildings is reviewed on an annual basis. 2009 levy will be revised as part of the university’s broader budget process.



Copyright | Disclaimer | Privacy | Contact ANU

Please direct all enquiries to: Ask ANU
Page authorised by: Director, Corporate Information Services

The Australian National University - CRICOS Provider Number: 00120C